Skill: Get Tasks Assigned to a Person Across Projects
Learn how to find all tasks assigned to a specific person across multiple projects in a portfolio
There is no cross-board query in the monday.com API. To find all tasks assigned to a specific person across projects in a portfolio, you need to iterate over each project's tasks board and filter by assignee.
Step 1 — Get all tasks board IDs from the portfolio
Follow Step 2 of the List All Projects in a Portfolio skill to extract all tasks board IDs from the portfolio's portfolio_project_link column:
{
boards(ids: [PORTFOLIO_BOARD_ID]) {
columns {
id
settings_str
}
}
}Parse settings_str for the column with id: "portfolio_project_link" to get the boardIds array.
Step 2 — Query each tasks board for assigned items
For each tasks board ID, use items_page_by_column_values to filter by assignee:
{
items_page_by_column_values(
limit: 50,
board_id: TASKS_BOARD_ID,
columns: [{ column_id: "project_owner", column_values: ["USER_ID"] }]
) {
cursor
items {
id
name
board { id name }
column_values(ids: ["project_owner", "project_dependency"]) {
id
type
text
}
}
}
}Repeat this query for each board ID. Use cursor for pagination if a single board has more than 50 tasks.
Important notes
project_owneris the consistent column ID for the assignee on tasks boards — no per-board column inspection is needed.- This approach requires O(n) requests where n is the number of projects in the portfolio. If you only need tasks across a known subset of projects, pass only those board IDs.
items_page_by_column_valuesrequires a singleboard_id— multi-board filtering is not supported.query_paramsrules do not work for people columns. Always useitems_page_by_column_valuesfor person-based filtering.
Updated 3 days ago